North West Point Distribution Plant and Transmission Mains North West Point Water Production Plant (NWP)…
Current Work of 21st August 2024
Beechwood Line Connection
Completion of tie-in – August 23rd 2024
Valve Replacement Project
Replacement of remaining Main Valves should be completed by October 30th 2024.
Five Cays/South Dock Main Extension
- Analysis of materials order and lead time obtention. – August 9th 2024
- Pie laying has started with remaining 6” C900 pipe in South Dock area.
- Completion of project – 3 months after receipt of materials – Expected date – November 2024