Beechwood Line Connection Completion of tie-in – August 23rd 2024 Valve Replacement Project Replacement of…
Update on North West Point Distribution Plant and Transmission Mains
North West Point Distribution Plant and Transmission Mains
- North West Point Water Production Plant (NWP) land clearing has begun and test wells have been executed.
- Distribution design is being completed and final design has been completed. (August 2nd 2024)
- Material and machinery procurement procedure has begun and is being fine-tuned. Purchase order was sent on August 9th.
- NWP plant completion date – December 2025
- NWP plant Distribution line installation and completion – December 2025